Resource Optimization Notes: Definitions & Explanations PDF | Download eBooks
Study Resource Optimization lecture notes PDF with project management definitions and explanation to study “What is Resource Optimization?”. Study resource optimization explanation with project management terms to review project management course for online MBA programs.
Resource Optimization Definition:
Resource optimization is used to adjust the start and finish dates of activities to adjust planned resource use to be equal to or less than resource availability.
A Guide to the Project Management Body of Knowledge by Project Management Institute
Resource Optimization Notes:
As a project is a resource-limited endeavor, the available resources for a project must be utilized effectively. Resource utilization is the process of adjusting the use of resources according to the availability. Usually, same resources are needed for different activities. To make the resources available for each activity provides the basis for resources utilization. This is usually done by adjusting the start and end dates and time of the activities. Different resource optimization techniques are used in project management to balance the demand and supply of the resources. One technique is called resource leveling which involves start and finish dates of the activities are adjusted to make the resources available. Another technique is called resource smoothing that involves adjusting the activities in a way that the required resources does not exceed the limit.
Keep Learning with Project Management Notes
What is Award Cycle?
After the requirements are identified, the needed products or services are acquired by selecting the appropriate acquisition method. The final ...
What is Life Cycle Leadership Model?
Leadership is an important aspect of a project manager's behavior. A project manager must possess excellent leadership skills to motivate ...
What is Matrix Diagram?
As the name indicates, matrix diagrams involve rows and columns like a matrix and tend to identify the impact of ...
What is As Soon as Possible Schedule?
After planning the project, the project is divided into associated tasks and activities using a work breakdown structure. These activities ...
What is Project Portfolio Management?
To provide comfort to the project manager and upper management of the organization, project management softwares are introduced. These softwares ...
What is Reserve Analysis?
After estimating the duration and cost estimates, it is important to consider the situations of uncertainty. Based on the uncertainty ...