Lead Definition:
A lead is defined as the amount of time a successor activity can be advanced with respect to a predecessor activity.
A Guide to the Project Management Body of Knowledge by Project Management Institute
Lead Notes:
While scheduling a project's activities, it is important to understand the relationship between the activities i.e. the dependencies. Schedule and dependencies are closely linked to completion time of activities and ultimately, the overall project's successful and timely completion. The activities can either be accelerated or delayed during a project accordingly. The amount of time for which an activity can be accelerated with respect to the activity prior to it is called lead. Lead is a very important concept in project network diagrams. Lead basically shows the overlap of two activities. For example, if activity B is started when activity A of the project is half-finished, the amount of time by which activity B is advanced is called lead. Lead is added as a negative value.
Keep Learning with Project Management Notes
What is Accessibility?
A project manager is responsible to carry out a project effectively, efficiently, and successfully. There are different roles and responsibilities ...
What is Life Cycle Cost Analysis?
Life cycle costing involves calculating the costs of the product throughout its life for decision making. The costs associated with ...
What is Budgeting and Cost Management Feature?
Different project management softwares are used in the field of project management. A number of features are available in these ...
What is Change Request?
During a project, there arise situations when changes in the project are to be made. The changes can be based ...
What are Prevention Costs?
When an organization focuses on quality management. Some costs are incurred. These costs are called costs of quality. The parts ...
What is Variance?
Variance is generally defined as deflection, deviation or inconsistency from a planned path. Variance in project management refers to the ...