Resource Smoothing Definition:
Resource smoothing is a technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits.
A Guide to the Project Management Body of Knowledge by Project Management Institute
Resource Smoothing Notes:
A project can need more resources than available. This means that the resources are limited for a particular project.Limited resources must be utilized effectively so that the project can be successfully completed. The process of effective use of resources is called resource utilization. Different resource optimization techniques are used in project management to balance the demand and supply of the resources. One technique is called resource smoothing. Resource smoothing is a process that tends to adjust the project activities so that the required resources does not exceed the already defined limit of the resources. The resource smoothing technique does not affect the critical path of the project. Although, it adjusts the activities but the project activities are only delayed according to the available slack. Resource smoothing, sometimes, fail to optimize all the project resources.
Keep Learning with Project Management Notes
What are Time Management Skills?
A project manager must possess time management skills. A project is time specific. It involves a lot of tasks and ...
What is Forecasted Cost at Completion?
As the cost performance is tracked regularly, it can be forecasted what the actual cost will be at the end ...
What is Reporting Period?
When a contract is made with the contractor and the project starts, it is important to check whether the actual ...
What is Earliest Start Time?
While dividing a project into its associated tasks and activities, it is important to determine the estimated time for each ...
What is Common Cause Variation?
A process can have different types of variations. A type of process variation that has known or unknown causes and ...
What is Management Section of a Proposal?
Every project requires a proposal from a contractor. There are three sections of a project proposal. One of them is ...