Study Finish to Finish lecture notes PDF with project management definitions and explanation to study What is Finish to Finish?. Study finish to finish explanation with project management terms to review project management course for online MBA programs.

Finish to Finish Definition:

Finish to Finish Notes:

When the project's schedule is to be developed, relationship between the project activities are established first. These relationships are logical and must be understood well. The relationships can be explained on the basis of predecessor and successor activity. A Predecessor activity is the one that logically comes before an activity in a schedule while successor activity is the one that comes after an activity. One of the relationships that can be established between project activities is called finish to finish (FF). Finish to finish is a logical relationship which shows that a successor activity cannot be finished unless the predecessor activity is finished. For example, writing an article (predecessor) must be finished before the article editing (successor) is finished.

Keep Learning with Project Management Notes

What is Process Analysis?

As the name indicates, process analysis considers a particular process and examines it in order to find any area of ...

What is Impact Influence Grid?

Different techniques can be used to represent the data and information that is collected for the key project stakeholders. A ...

What is Quality Management Plan?

Just as important it is to complete the project on time and provide the required deliverables to the customer, it ...

What is Risk Assessment?

Every project has some uncertainty. It is important for the project team to identify and assess all the risks associated ...

What is Cost Benefit Analysis?

In management, selecting and qualifying projects is important. It means to determine the worth of a project. Several methods are ...

What is Dummy Activity?

In the format of network diagram related to activity on arrow, sometimes a dummy activity is introduced in the diagram. ...