Study Precedence Diagramming Method lecture notes PDF with project management definitions and explanation to study What is Precedence Diagramming Method?. Study precedence diagramming method explanation with project management terms to review project management course for online MBA programs.

Precedence Diagramming Method Definition:

  • Precedence diagramming method (PDM) is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

    A Guide to the Project Management Body of Knowledge by Project Management Institute



Precedence Diagramming Method Notes:

When the project's schedule is to be developed, the most important thing is to identify the relationship between the project activities and tasks. Different tools and techniques can be used to achieve this goal. One of the tools is called precedence diagramming method. Precedence diagramming method involves the graphical representation of the project's activities (shown as nodes) and their relationship (through arrows). The relationship basically determines the sequence of the activities to be performed. Different relationships can be established between the activities. These include finish to start (FS), finish to finish (FF), and start to start (SS), start to finish (SF). In precedence diagramming method, two activities can have two different relationships, however, multiple relationships are not recommended and the relationship with highest impact must be selected for easiness.

Keep Learning with Project Management Notes

What is Managing Quality?

When a quality management plan is developed for a project, it is necessary to implement the plan by performing the ...

What is Decomposition?

The project related activities must be defined clearly in order to perform them efficiently and successfully complete the project. In ...

What is Direct and Manage Project Work?

The processes involved in executing process group involve the actual performance of the planned work which is required to achieve ...

What is Required Completion Time?

When a project is started, the total time required for a project to complete successfully must be estimated by the ...

What is Three Point Estimate?

A project is decomposed into its associated activities in order to estimate the activity durations and associated costs. The project ...

What is Project Quality Management?

Quality management and project management have been integrated as per the requirements of the modern world. Quality of a project ...