Precedence Diagramming Method Definition:
Precedence diagramming method (PDM) is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
A Guide to the Project Management Body of Knowledge by Project Management Institute
Precedence Diagramming Method Notes:
When the project's schedule is to be developed, the most important thing is to identify the relationship between the project activities and tasks. Different tools and techniques can be used to achieve this goal. One of the tools is called precedence diagramming method. Precedence diagramming method involves the graphical representation of the project's activities (shown as nodes) and their relationship (through arrows). The relationship basically determines the sequence of the activities to be performed. Different relationships can be established between the activities. These include finish to start (FS), finish to finish (FF), and start to start (SS), start to finish (SF). In precedence diagramming method, two activities can have two different relationships, however, multiple relationships are not recommended and the relationship with highest impact must be selected for easiness.
Keep Learning with Project Management Notes
What is Staffing?
A project manager is responsible to communicate with, motivate and encourage the team members to carry out a successful project. ...
What is Proposal?
When a customer requests for proposal, contractors respond in the form of a detailed document outlining the method of fulfilling ...
What is Final Report?
A written communication tool that is used throughout the project to communicate project related information is report. One of the ...
What is Three Point Estimate?
A project is decomposed into its associated activities in order to estimate the activity durations and associated costs. The project ...
What is Risk?
Every project has some uncertainty. There is always a chance that an unfortunate event might happen during the project. This ...
What is Successor Event?
Generally, a successor event refers to an event that immediately follows a previous event without any intervention. A successor event ...