Precedence Diagramming Method Definition:

  • Precedence diagramming method (PDM) is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

    A Guide to the Project Management Body of Knowledge by Project Management Institute



Precedence Diagramming Method Notes:

When the project's schedule is to be developed, the most important thing is to identify the relationship between the project activities and tasks. Different tools and techniques can be used to achieve this goal. One of the tools is called precedence diagramming method. Precedence diagramming method involves the graphical representation of the project's activities (shown as nodes) and their relationship (through arrows). The relationship basically determines the sequence of the activities to be performed. Different relationships can be established between the activities. These include finish to start (FS), finish to finish (FF), and start to start (SS), start to finish (SF). In precedence diagramming method, two activities can have two different relationships, however, multiple relationships are not recommended and the relationship with highest impact must be selected for easiness.

Keep Learning with Project Management Notes

What are External Failure Costs?

Organizations, nowadays, are adopting quality management. When the products of an organization are monitored to make them according to the ...

What is Requirements Documentation?

A project's requirements must be established before the project starts. These requirements should be documented. Requirements documentation gives the details ...

What is Win Ratio?

When trying to submit a proposal in response to request for proposal, a contractor assesses its previous performance, both for ...

What is Payback Period?

A project must be selected based on a pre-defined selection criteria. A way of selecting a project is to compare ...

What is Quality Policy?

Although it is important to provide the deliverables to the customer and complete the project on time, but the results ...

What is Manufacturing Break?

As the name indicates, manufacturing break is the time between two manufacturing orders. When a manufacturing order is completed, the ...