Schedule Performance Index Definition:
Schedule performance index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value.
A Guide to the Project Management Body of Knowledge by Project Management Institute
Schedule Performance Index Notes:
It is important to monitor if the actual work performed is according to the plan/schedule. The schedule performance of a project is analyzed using different performance measures. One of the schedule performance indicator is called schedule performance index. It shows how efficiently the project is performed till the specific point in time. Schedule performance index is a ratio of earned value to planned value. Schedule performance index is usually used in combination with cost performance index. Schedule performance index of 1.0 shows that more work has been accomplished in relation to the planned schedule. The schedule performance index of the critical path must be analyzed to know if the overall project will be completed on, before or after the planned finish date.
Keep Learning with Project Management Notes
What is Matrix-Type Organization?
A matrix type organization is a combination of functional organization and project-type organization. Although the matrix type organization focuses on ...
What is Cost Estimate?
A specific cost is associated with each and every activity of the project. These costs must be estimated to develop ...
What is Project Management Plan?
Project management is basically the application of different tools and skills etc. to carry out a project. As project management ...
What is Quality?
In case of project management, the quality of the deliverables must be good to achieve customer satisfaction. Quality is the ...
What are Internal Failure Costs?
Everything comes with a cost. When an organization tries to reduce the costs associated with non-conforming products, still costs related ...
What is Stakeholder Engagement Planning?
The major aim of identifying project stakeholders at an early stage of the project is to improve their engagement in ...